Cost Reimbursable procurement category

Cost Reimbursable procurement is used where there is uncertainty as to project scope and design definition, or there are unknown or unquantifiable risks and complex interfaces to be managed that cannot be effectively priced or programmed on a lump sum or fixed price basis.

The Cost Reimbursable procurement category recognises that specific risks are allocated to the party best able to manage them.

Requirements

Cost Reimbursable projects must be delivered in accordance with Cost Reimbursable Procurement Requirements and associated contracts, guidance and templates.

The Cost Reimbursable Procurement Requirements provide further information on implementing its specific procurement models.

Cost Reimbursable Procurement Requirements
PDF 781.56 KB
(opens in a new window)
Cost Reimbursable Procurement Requirements
Word 5.48 MB
(opens in a new window)

Cost reimbursable procurement models

The three cost reimbursable procurement models are:

  1. Incentivised Target Cost (ITC) is a model that includes a development phase where the contractor develops a Target Outturn Cost and a delivery phase where the contractor proceeds on an open‑book basis where the State reimburses the contractor for actual incurred costs of performing the works and a percentage for corporate overhead and profit.
  2. Managing Contractor is a model where the delivery agency engages a managing contractor (MC) who is responsible for all aspects of project delivery, including managing the completion of design and construction documentation and tendering and awarding trade packages.
  3. Allianceis a model where the delivery agency and non-owner participants (NOPs), comprising the contractor, designer and other contracted parties work together to design and construct a project.

Supporting deeds and guidance notes

Incentivised Target Cost Contract Suite - Commercial Principles - September 2023
PDF 616.2 KB
(opens in a new window)
Incentivised Target Cost Contract Suite - Commercial Principles - September 2023
Word 4.35 MB
(opens in a new window)
Incentivised Target Cost Contract Suite - Guidance Notes - September 2023
PDF 947.62 KB
(opens in a new window)
Incentivised Target Cost Contract Suite - Guidance Notes - September 2023
Word 5.28 MB
(opens in a new window)
Incentivised Target Cost Development Deed
Word 444.03 KB
(opens in a new window)
Incentivised Target Cost Delivery Deed
Word 1.07 MB
(opens in a new window)
Incentivised Target Cost Delivery Deed - Schedule 3 - Reimbursable Costs
Word 85.34 KB
(opens in a new window)
Incentivised Target Cost Delivery Deed - Schedule 5 - Risk or Reward Regime
Word 45.85 KB
(opens in a new window)
Incentivised Target Cost Delivery Deed - Schedule 14 - Relevant State Policies
Word 91.06 KB
(opens in a new window)
Incentivised Target Cost Delivery Deed - Schedule 15 - Adjustment Event Schedule
Word 41.21 KB
(opens in a new window)
Incentivised Target Cost Delivery Deed - Schedule 22 - Executive Review Group Terms of Reference
Word 50.68 KB
(opens in a new window)

For more information on the Incentivised Target Cost contract, please contact infrastructure.delivery@dtf.vic.gov.au.